Harrow Strategic Development Partnership (HSDP) - Review and Progress

18/11/2022 - Harrow Strategic Development Partnership (HSDP) - Review and Progress

Having considered the confidential Appendix, and the reference from the Overview and Scrutiny Committee, it was

 

RESOLVED:  That

 

(1)            the outcome of the review of the Harrow Strategic Development Partnership (HSDP) sites be noted;

 

(2)            further reports on the phase Business Plans for each scheme be authorised and agreed;

 

(3)            Greenhill Way be the preferred location for the Town Hall;

 

(4)            the initial Business Plan for Grange Farm (Phase 2) be agreed;

 

(5)            the Grange Farm scheme be incorporated into the HSDP and the development of a planning application for Phases 2 and 3 be approved;

 

(6)            the decision to revise the HSDP schemes be confirmed and officers be authorised to commission appropriate professional services and carry out preparatory and enabling works; and

 

(7)            Cabinet consider the production of a report on the economic impact of the proposals for the Greenhill Way site.

 

Reason for Decision:  To understand the outcomes of the review of the HSDP sites, authorise preparation of business plans for the revised schemes, allow further works required to provide a new Town Hall and agree the business plan and way forward for Grange Farm in order that high quality new housing can be developed for the Council’s tenants and residents.