Having noted the confidential appendix to the report, Cabinet
RESOLVED: That
(1) progress on Phase 1 Grange Farm be noted;
(2) the principle of appointing the Harrow Strategic Development Partnership (HSDP) to take forward the redevelopment of Phase 2 and 3 Grange Farm, be agreed; and
(3) the Corporate Director of Community be authorised to commission the HSDP to develop a detailed Business Plan which would be brought back to Cabinet for final approval.
Reasons: To enable delivery of the Grange Farm estate regeneration project.
Alternative Options Considered and Rejected: As set out in the report.